MDOT has been working closely with the contractor and beam manufacturer to get the new bridge beams manufactured and delivered. MDOT has received confirmation that the new beams have been manufactured, and the tentative delivery and installation dates are set.
The new beams will be delivered and placed on the nights of August 5th and August 6th. The exact open to traffic date is unknown, but MDOT is working closely with the contractor to have the bridge open by mid-November pending weather or any unforeseen issues.